Most Projects Run Over Budget. Does Yours Know by How Much?

November 9 · Written By Michele Gray

Pull the last ten closed jobs and put each original estimate next to its final cost. Most owners have never done it. The estimate gets written, the job gets done, the invoice goes out, and nobody lines the two numbers up. That gap is where margin goes missing, and it is more predictable than it feels.

The idea: overrun is the rule, not the exception

Bent Flyvbjerg, an Oxford professor who studies large projects, assembled data on 258 transportation infrastructure projects in 20 nations on five continents. His finding, in his words: "9 out of 10 projects have cost overrun." He also reports that the overrun was "constant for the 70-year period covered by the study," meaning it did not get better as planning tools improved.

The average overruns, in constant prices and measured from the decision to build, were 44.7 percent for rail (58 projects), 33.8 percent for bridges and tunnels (33 projects), and 20.4 percent for roads (167 projects).

Two cautions before we borrow this. These are large public transportation projects, not water damage jobs, and the numbers are not a restoration benchmark. Do not tell a customer or a lender that restoration jobs run 20 percent over. Second, the baseline matters. Flyvbjerg measures from the decision to build, the number everyone committed to. Change the baseline and you change the overrun.

The useful lesson is the pattern. When the outcome is one-sided, nine times in ten, "bad luck" stops being an explanation. It is how the work behaves.

The restoration translation

Restoration has its own version of the baseline problem. The number everyone commits to is the first scope, written when you can see only the surface. The wall comes open, the moisture reading travels further than expected, the subfloor is wet. The real job is discovered after the number is set.

Here is what that does, as an illustration with made-up numbers, not client data. A job is priced at $20,000 with an expected direct cost of $14,000, a 30.0 percent gross margin.

The revenue side of that sentence matters. If the extra work becomes a supplement you documented and got approved, the overrun is just a bigger job. If it becomes work you absorbed to keep things moving, it is margin lost. The difference between those two outcomes is the thing worth measuring, and it only shows up when you compare the original estimate with the final cost and the final bill.

We have written about the mindset side of this in why your jobs run long and why confident estimates cost margin. This post is the measurement side.

Four moves

  1. Keep an estimate-versus-actual log. One row per closed job: original estimate, final direct cost, original price, final billed amount. Four numbers, kept in your job costing system or even a spreadsheet. Ten jobs is enough to see a pattern.
  2. Split the gap in two. Cost growth that was billed through an approved supplement is one bucket. Cost growth you absorbed is the other. Only the second is a leak, and you cannot fix a leak you have lumped together with healthy growth.
  3. Sort by division. Mitigation, reconstruction, contents and mold do not overrun the same way. A blended average hides which one is carrying the pattern. Our post on supplements as change orders covers how to treat the billed side.
  4. Re-estimate at the moment of discovery. When demo reveals the real scope, write the new number that day, before the crew is further along. Nine in ten is a reason to expect the surprise, so decide in advance who updates the estimate and who sends the supplement.

What this is not

It is not a call to inflate your estimates. A padded number is still a single guess, and it can cost you the job. It is a call to learn your own overrun pattern from your own closed jobs, then price and staff with that pattern in view. Your history is a better benchmark than anyone else's.

If you want help turning closed-job history into margin floors and a monthly review, that is part of what restoration CFO services are built for, and you can reach out here to talk it through.

General education for restoration and reconstruction owners, not tax, legal, investment, or insurance advice. Your market and numbers will differ, so confirm specifics for your situation.

Want to see where your restoration profit is really going?

We build the job costing, cash forecast, and monthly reporting that turn “we were busy” into “we made money.” Restoration and reconstruction is all we do.

Sources: Flyvbjerg, B. (2013). "Survival of the Unfittest: Why the Worst Infrastructure Gets Built, And What We Can Do about It." arXiv:1303.6571 (arxiv.org/abs/1303.6571), retrieved November 9, 2026. Figures cited: 258 projects, 20 nations, five continents, 70-year period, "9 out of 10 projects have cost overrun," and average overruns for rail (44.7%, N=58), bridges and tunnels (33.8%, N=33) and roads (20.4%, N=167). These are transportation infrastructure data, not restoration data. The $20,000 job and its cost figures are a Kiwi illustration with arithmetic checked by script, not client or industry data. The restoration application is practice and opinion.